Commercial and Industrial CDCs in NSW: Fit-Outs, Change of Use and New Warehouses Without a DA
Most writing about complying development is about houses. This guide is about the other half: shop and office fit-outs, cafés, gyms, warehouses, factories and business parks. It explains when commercial work is exempt, when it can be approved by a CDC under the Industrial and Business Codes in weeks, when it needs a DA, and the BCA and fire safety triggers that decide whether a “simple” fit-out or change of use stays simple. Written by the registered certifiers at Built Smart Solutions in Sydney.
CURRENT AS AT 2 OCTOBER 2026
21 MIN READ
BY BUILT SMART SOLUTIONS
SEO/AI under the hood (amended per review actions 2 & R4): exact-match H1 restored per audit 2.1 – the personality line survives as the subhead · URL /services/certification/ per the audit keyword map · meta description: “Principal Certifier Appointment, Construction & Occupation Certificates and Complying Development (CDC) from one specialist, ISO 9001-certified team – approval to occupation.” (adopted from Option 1’s written set) · the “Quick Answer” block is deliberately extractable – it’s the sentence we want ChatGPT/Gemini/AI Overviews to quote · FAQPage + Service schema · 800+ words at full build · division-coded breadcrumb.
Quick answer
In NSW, commercial and industrial work can follow three pathways. Exempt development needs no approval: some non-structural internal fit-outs, and a listed change of use where the existing use is lawful, the new use is permissible and not on the excluded list (food and drink premises are excluded), the NCC building classification does not change (other than between Class 5 and Class 6) and no non-exempt building work is done. Complying development covers larger internal alterations, changes of use, new industrial and business buildings and additions that meet the standards in the Codes SEPP Part 5 (Industrial and Business Alterations Code) and Part 5A (Industrial and Business Buildings Code). A registered certifier or council must usually determine a commercial or industrial CDC within 10 days; the period is 20 days if the application includes demolition under the Demolition Code, or a new dwelling such as a caretaker’s flat, on a lot in most of metropolitan Sydney within 20 m of a lot with a dwelling. Anything that falls outside those codes, or sits on excluded land, needs a development application.
Whatever the pathway, the building must comply with the National Construction Code for the use, so changes of use and fit-outs often trigger fire safety, egress and accessibility upgrades. The certification fee is set by the scope, not a list price: the building class, the size of the works, any change of BCA classification, the fire safety measures involved and the number of inspections, plus BCA and fire safety input where needed. Built Smart Solutions confirms the pathway, issues commercial and industrial CDCs as registered certifiers, and brings BCA, fire safety, access and traffic advice into one team.
Key takeaways
- Three pathways, not two. Some commercial fit-outs and changes of use are exempt, many are CDC, the rest are DA. Check in that order.
- The building classification is the hinge. If the new use changes the NCC class (for example a warehouse becoming a gym), the change of use is not exempt (the only exception is between Class 5 and Class 6), and for a CDC the building must meet the Category 1 fire safety provisions for the new use.
- Two codes do most of the work: Part 5 (Industrial and Business Alterations Code) for alterations, and Part 5A (Industrial and Business Buildings Code) for new buildings, additions, change of use and site works.
- Zones were renamed in 2023. The old B and IN zones became employment zones E1 to E5 and MU1. The codes list the new names alongside the old ones; your LEP uses the new ones.
- Fire safety decides the budget. Egress, fire separation, sprinklers, hydrants and the fire safety schedule are where commercial CDCs succeed or stall.
- Lease last, pathway first. Confirm the approval pathway and upgrade cost before signing a lease or buying a building.
- One team helps. Built Smart Solutions handles the certification, BCA, fire safety, access and traffic input in-house, so the CDC is not held up waiting on consultants who never spoke to each other.
Exempt, CDC or DA: the three pathways for commercial work
The State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 (the Codes SEPP) sets two of the three pathways; the third is a development application under the Environmental Planning and Assessment Act 1979. Our CDC vs DA guide covers the general decision; this table shows how it plays out for commercial and industrial work.
| Pathway | Typical commercial work | Who approves | Timeframe | Key condition |
|---|---|---|---|---|
| Exempt development | Non-structural internal fit-outs; listed changes of use with no change in NCC classification (other than Class 5 to Class 6 or back) and no non-exempt building work | No approval | Immediate | Every exempt standard met; existing use lawful |
| Complying development (CDC) | Internal alterations, shopfronts, change of use, first use, new industrial and business buildings, additions, site and parking upgrades | Registered certifier or council | Usually a 10-day statutory determination period on a complete application | Every standard in Part 5 or 5A met; land not excluded |
| Development application (DA) | Anything outside the codes: excluded land, non-listed uses, larger or non-compliant buildings, heritage items, hazardous or offensive industry | Consent authority (usually the council or a planning panel) | Commonly several months for commercial work in Sydney, plus a Construction Certificate | Merit assessment |
“Exempt” is the most misused word in commercial leasing. An agent’s “you don’t need approval, it’s just a fit-out” is not advice. If the work touches structure, fire safety, egress, services or the building classification, it is almost certainly not exempt. Get exempt development advice in writing before you rely on it.
The Industrial and Business Codes explained
Commercial and industrial complying development sits mainly in two parts of the Codes SEPP, which were expanded by the Building Business Back Better reforms that commenced on 1 February 2022, and were later updated to refer to the employment zones.
| Provision | What it covers | Typical projects |
|---|---|---|
| Part 2, Subdivision 10A (exempt) | Change of use of premises as exempt development, subject to strict conditions | Listed pairings, such as shop, office and business premises to one another, or light industry to warehouse, with no non-exempt works |
| Part 2 (other exempt subdivisions) | Minor non-structural internal alterations, signage and minor works | Painting, joinery, carpets, non-structural partitions that do not affect fire safety or egress |
| Part 5: Industrial and Business Alterations Code | Internal alterations that do not increase gross floor area, shopfronts and awnings, mechanical ventilation, signs and other minor works to existing buildings | Office and retail fit-outs, shopfront replacement, internal reconfiguration |
| Part 5A: Industrial and Business Buildings Code | New industrial and business buildings, additions, first use and change of use of premises, internal alterations, site works and parking | New warehouses and factories, extensions, warehouse to gym, shop to café, office to health consulting rooms or a medical centre |
| Part 8: Fire Safety Code | Certain fire safety upgrades to existing buildings | Upgrades required following an audit or order |
| Part 7: Demolition Code | Demolition of non-excluded buildings | Strip-outs and demolition ahead of a new building |
Within Part 5A, the zone-specific building standards (height, setbacks, landscaping and the like) apply only where the development involves building work, and not to internal alterations that do not increase gross floor area. A change of use still has to meet the general standards that apply to every Part 5A development, including parking, any new loading or driveway works, and the caps for particular uses, and the building still has to meet the fire safety requirements for the new use. Part 5A also covers only listed purposes, its “specified purposes”, and excludes others outright, including pubs, small bars, registered clubs and potentially hazardous or offensive industries. New buildings are not covered in Zones E1, E2 or MU1. So the first check is always whether your proposed use and zone are covered.
Employment zones: E1 to E5, MU1 and what they allow
In April 2023 NSW replaced the old business (B) and industrial (IN) zones with employment zones. Leases, older approvals and many websites still use the old names, which causes confusion. The Codes SEPP lists both the new and the old names.
| New zone | Name | Broadly replaced | Typical uses |
|---|---|---|---|
| E1 | Local Centre | B1 Neighbourhood Centre, B2 Local Centre | Shops, cafés, services, small offices, shop-top housing |
| E2 | Commercial Centre | B3 Commercial Core | Offices, retail, entertainment in major centres |
| E3 | Productivity Support | B5 Business Development, B6 Enterprise Corridor, B7 Business Park and some IN2 | Bulky goods, light industry, creative industries, offices, gyms, trade supplies |
| E4 | General Industrial | IN1 General Industrial, IN2 Light Industrial | Warehouses, factories, depots, logistics |
| E5 | Heavy Industrial | IN3 Heavy Industrial | Heavy and hazardous industry (often outside CDC) |
| MU1 | Mixed Use | B4 Mixed Use | Retail and commercial with residential above |
Zone permissibility comes from the council’s LEP; the Codes SEPP then says which of those permitted uses can be approved as complying development. A use can be permitted in the zone and still need a DA because the code does not list it. A planner or certifier confirms both from the LEP and the section 10.7 certificate.
Fit-outs: when they are exempt and when they need a CDC
A fit-out is not a legal category; it is a description of work. Whether it needs approval depends on what the work touches.
| Fit-out work | Likely pathway | Why |
|---|---|---|
| Painting, flooring, joinery, furniture, loose fittings | Exempt | No structure, services or fire safety affected |
| Non-structural partitions that do not change exits, travel distances or fire separation | Often exempt | Subject to the exempt standards; egress must not be affected |
| New partitions that change exit paths, travel distances or room layouts | CDC (Part 5 or 5A) | Egress and fire safety must be reassessed against the NCC |
| New or relocated amenities, kitchens, plumbing and mechanical services | CDC | Services and NCC health and amenity provisions |
| Structural work, mezzanines, openings in walls or floors | CDC under Part 5A (within its limits) or DA; Part 5 does not allow added floor area, other than to meet the Premises Standards | Structure, fire separation and floor area |
| Shopfront replacement | CDC, sometimes exempt | Depends on the code standards and heritage |
| Fit-out in a heritage item | DA | Heritage items are excluded from complying development, apart from limited Heritage Act exemptions |
| Fit-out combined with a change of use that changes NCC class | CDC or DA | Not exempt; for a CDC the building must meet the Category 1 fire safety provisions for the new use |
The trigger most people miss is egress. A fit-out that subdivides a tenancy, adds meeting rooms or closes a corridor can push travel distances to an exit beyond the NCC limits, or leave a room with only one exit where two are required. Our BCA consultant guide explains why fit-outs are the most common way a compliant building becomes non-compliant.
Change of use: exempt, CDC or DA
A change of use happens when premises start being used for a different purpose: a warehouse becomes a gym, a shop becomes a café, an office becomes a clinic, a factory becomes a self-storage facility. It needs approval even if no building work is done, unless it qualifies as exempt.
When a change of use is exempt
Under Part 2, Subdivision 10A of the Codes SEPP, a change of use can be exempt development only if it is one of the listed pairings (for example shop to office, office to business premises, or light industry to warehouse) and every standard is met: the existing use is lawful and does not rely on existing use rights; the new use is permissible with consent; the building’s classification does not change, other than between Class 5 and Class 6 where the building meets the code for the new use; the new use is not on the excluded list, which includes food and drink premises, hair and beauty salons and skin penetration premises; no building work is carried out other than exempt work; gross floor area does not increase; and existing consent conditions on matters such as parking, traffic and waste, and in some zones hours, are not breached.
When a change of use can be a CDC
Where a change of use is not exempt, Part 5A allows first use and change of use of premises to specified uses in specified zones as complying development, subject to the code’s requirements. Typical CDC changes of use in Sydney include warehouses to gyms or indoor recreation, light industrial units to creative industries or trade showrooms, and vacant shops to food and drink premises. Watch the caps: indoor recreation facilities such as gyms are limited to 1,000 m² of gross floor area, and food and drink premises to 100 patrons.
When a change of use needs a DA
A DA is needed when the new use is not listed for complying development in that zone, the land is excluded, the premises are a heritage item, or the use falls into a category the code excludes (for example hazardous or offensive industry). Childcare centres, places of public worship, pubs, small bars and registered clubs fall here, because they are not specified purposes under Part 5A. Health consulting rooms and medical centres, by contrast, are specified purposes and can be complying development where permissible.
| From | To | NCC class change | Likely pathway | Typical upgrade triggers |
|---|---|---|---|---|
| Shop | Shop (different retailer) | None (Class 6 to 6) | Often exempt | None if no works |
| Office | Office | None (Class 5 to 5) | Often exempt | None if no works |
| Warehouse | Gym / indoor recreation | Class 7b to Class 9b (assembly building for recreational or sporting purposes) | CDC (Part 5A) where permissible and no more than 1,000 m², else DA | Occupant load, exits, sanitary facilities, accessibility, fire services |
| Shop | Café or restaurant | Class 6 to Class 6, higher occupant load | CDC (Part 5A) up to 100 patrons, else DA | Exhaust, grease trap, sanitary facilities, patron cap, operating hours |
| Factory | Warehouse / storage | Class 8 to Class 7b | CDC (Part 5A) | Fire compartment size, sprinklers, hydrant coverage |
| Office | Medical or health consulting | Class 5 to Class 5 or 9a depending on services | CDC (Part 5A) where permissible, else DA | Accessibility, sanitary facilities, sometimes health care class provisions |
| Commercial | Childcare | To Class 9b | DA | Whole-of-building fire, egress, access, acoustic |
Our fire safety consultant guide explains why changes of use are where fire safety upgrades most often appear.
New warehouses, factories and additions
Part 5A allows new industrial and business buildings and additions to existing ones to be approved as complying development in industrial zones and some business zones (new buildings are not covered in Zones E1, E2 or MU1), provided every development standard is met. In industrial zones the code now allows buildings of up to 50,000 m² of gross floor area, and the standards cover, among other things:
- Building height and gross floor area limits for the zone and lot.
- Setbacks to the street, side and rear boundaries, with greater setbacks and interface controls where the site adjoins a residential zone.
- Landscaping to the street frontage and boundaries.
- Car parking, loading and vehicle access, including manoeuvring for the design vehicle.
- Stormwater, earthworks and retaining walls.
- External finishes and design requirements, including a design statement by a qualified designer for buildings in Zone E3 and the former B5 to B7 zones.
- Hours of operation, set by the CDC conditions where no existing consent condition applies, and other operational conditions for the use.
New warehouses and factories also bring in the full weight of NCC Volume One: fire compartment sizes, sprinkler and hydrant requirements, smoke hazard management, egress for large floor plates, and accessibility to offices and amenities. For a large-volume building, the BCA and fire strategy usually drive the design more than the planning standards. Our Western Sydney industrial and office case study shows how an early BCA upgrade and fire safety strategy kept a project on track.
Parking and loading are the planning standards new industrial buildings most often miss. Where the design cannot meet them, or council’s traffic engineer will need convincing on a DA, a traffic and parking assessment resolves it before lodgement.
BCA and fire safety triggers: where commercial CDCs stall
The planning standards decide whether a commercial project can be a CDC. The National Construction Code decides what it costs. These are the triggers that turn a “simple” fit-out or change of use into a building upgrade.
| Trigger | What it means | Typical consequence | Who resolves it |
|---|---|---|---|
| Change of NCC classification | The new use is a different class (for example 7b to 9b) | For a CDC, the building must have adequate egress and comply with the Category 1 fire safety provisions for the new use, with fire protection and structural capacity suited to it; upgrades likely | BCA consultant and certifier |
| Higher occupant load | More people (gyms, cafés, assembly uses) | More or wider exits, more sanitary facilities, travel distance checks | BCA consultant |
| Travel distance and exits | New partitions lengthen paths to exits | Layout changes or a performance solution | BCA consultant; fire engineer if needed |
| Fire compartment size | Large open floors, especially warehouses | Sprinklers, fire walls or a performance solution | Fire safety consultant |
| Fire services | Hydrant and hose reel coverage, detection, emergency lighting, exit signs | New or extended services and a revised fire safety schedule | Fire safety consultant and services contractor |
| Accessibility | Access to and within the building, accessible sanitary facilities | Ramps, lifts, accessible toilets, or a justified departure | Access consultant |
| Fire safety schedule and certificate | Measures listed on the schedule must be installed and certified | Fire safety certificate before the OC; annual statements thereafter | Certifier, accredited practitioner |
| Existing non-compliances | Problems already in the building are uncovered | On a change of use that changes the NCC class, the Category 1 fire safety provisions apply to the new use regardless; on alterations, fire protection and structural capacity must not be reduced, and a reconfigured part must have adequate egress | BCA consultant and certifier |
Ask for a short BCA and fire safety capability check before you sign a lease or exchange on a commercial building. It costs a fraction of one month’s rent and tells you whether the use you want needs a minor fit-out or a five-figure upgrade. Built Smart Solutions runs these as part of every commercial CDC fee proposal.
After the Occupation Certificate, the building owner carries ongoing obligations: maintaining every essential fire safety measure, having it inspected, tested and serviced to AS 1851-2012 where that standard addresses the activity (emergency and exit lighting sits under AS/NZS 2293), keeping the records on site for at least 7 years, and giving an annual fire safety statement. Our articles on annual fire safety statements and the 2026 fire safety reforms explain what that means for tenants and owners.
When a commercial CDC is not available
- Heritage items, apart from limited Heritage Act exemptions.
- Land excluded for the Industrial and Business Buildings Code, including heritage conservation areas, environmentally sensitive land and significantly contaminated land: new buildings and additions are excluded there, but a change of use or internal alterations can still be complying development.
- Environmentally sensitive areas and other land excluded for all complying development.
- BAL-40 and Flame Zone land, and flood or bushfire land that does not meet the code’s standards.
- Uses not listed for complying development in the zone, even if the LEP permits them.
- Hazardous or offensive industry, designated development and uses needing approvals the code excludes.
- Buildings or extensions beyond the code’s height, floor area or setback standards.
- Unapproved existing works or uses. A certifier cannot build on an unlawful starting point; it may need regularising first.
- Land subject to a restriction or a site-specific exclusion stated on the section 10.7 planning certificate.
When a CDC is not available, a well-prepared DA is the route. Built Smart Solutions’ town planning team handles commercial DA preparation and the Statement of Environmental Effects, including the staff numbers, hours, access, loading and waste details councils expect for a change of use.
Worked examples from Sydney projects
These composite examples reflect the kinds of commercial and industrial projects we see across Sydney. Details are generalised.
| Project | Pathway | What decided it | Outcome |
|---|---|---|---|
| Office tenancy refresh, open plan to meeting rooms, Parramatta | CDC (Part 5) | New partitions changed exit paths | Layout adjusted to keep travel distances compliant; CDC issued without a performance solution |
| Warehouse unit to boutique gym, Western Sydney (E4) | CDC (Part 5A) | Use covered in the zone and under the 1,000 m² cap; class change from 7b to 9b | Additional exit, accessible toilet and emergency lighting added; CDC issued |
| Vacant shop to café, Inner West (E1) | CDC (Part 5A) | Patron numbers within the code’s 100-patron cap | Exhaust, grease arrestor and sanitary facilities designed in; CDC issued |
| Retail to medical consulting rooms, North Shore | DA | Use not suited to the CDC pathway at that site | DA with access and parking reports |
| New 8,000 m² warehouse, South West Sydney (E4) | CDC (Part 5A) | Height, setbacks, landscaping and parking met | Fire strategy with sprinklers set early; CDC issued, partial occupation certificate for the first stage |
| Shop fit-out in a heritage-listed building, CBD | DA | Heritage item excluded | DA with heritage impact statement, then CC |
Commercial CDC costs, and what actually moves the number
Commercial and industrial certification is scoped work, not a list price. Two fit-outs of the same floor area can carry very different fees once the building class, the fire safety measures and the specialist input are known, and a range quoted without that scope tells you very little. What follows is what sets the fee, and what a proposal has to state before you can compare one to another. Construction is excluded.
| Factor | Why it moves the fee |
|---|---|
| The pathway | Exempt work needs no certificate. A CDC is assessed by the certifier as one certificate. A DA adds the council’s fee, a Statement of Environmental Effects and a separate Construction Certificate, and months of holding cost. |
| Use and building class | A change of use that changes the building’s BCA classification brings in the Regulation’s fire safety upgrade provisions, which widens the BCA and fire safety scope. |
| Size and type of work | Floor area, storeys and whether the work is a fit-out, an addition or a new building set the assessment and inspection effort. |
| Fire safety measures | New or altered essential fire safety measures need design, certification and a fire safety schedule, and often a fire engineer. |
| Access | Work affecting the path of travel can trigger access upgrades under the NCC and the Premises Standards, and an access report to support them. |
| Traffic and parking | New warehouses and some changes of use need traffic, parking and loading input. |
| Inspections | The critical stage inspections are set by the Regulation for the class of building and the work. |
| Contributions, Long Service Levy and government fees | Contributions apply where the council’s plan provides for them. The Long Service Levy is 0.25% of the cost of works of $250,000 or more. Lodgement, certificate and agency fees are set by government and change from time to time, so a proposal should list them as pass-through items rather than build them into the fee. |
What a comparable proposal has to tell you
- The BCA classification before and after. And whether the change brings in the fire safety upgrade provisions.
- Which code, or why not. The Codes SEPP part relied on, or the reason the work needs a DA or is exempt.
- What the fee covers. The CDC, the Principal Certifier appointment, each critical stage inspection, the fire safety certificate process and the Occupation Certificate.
- What it excludes. BCA, fire, access and traffic reports, contributions, the Long Service Levy and government fees, stated as excluded rather than simply left out.
- The turnaround. When the CDC will be determined once the application is complete, and the inspection notice period.
- A fixed fee against that scope, rather than an hourly rate with no cap.
Built Smart Solutions quotes every engagement as a fixed fee against a written scope, with the exclusions and the turnaround stated on the same page. Get a fee proposal.
For a commercial tenant, the biggest cost is rarely the approval fee. It is rent on a tenancy that cannot open. A CDC instead of a three-month DA can be worth more than the whole approval budget.
Timelines: CDC vs DA for commercial projects
| Stage | CDC | DA + CC |
|---|---|---|
| Pathway and capability check | A few days | A few days |
| Design, BCA and fire input | Usually a few weeks | Usually longer, plus the SoEE and reports |
| Assessment | Usually a 10-day statutory period on a complete application | Commonly several months, and longer for a new building |
| Construction approval | Included | A separate Construction Certificate after consent |
| Fit-out works and inspections | Project-dependent | Project-dependent |
| Fire safety certificate and OC | Once the works are complete and the final fire safety certificate is in | Once the works are complete and the final fire safety certificate is in |
About to sign a lease or buy a building?
Tell us the address and the use. Built Smart Solutions will confirm whether it is exempt, CDC or DA and what upgrades to expect, before you commit.
Common mistakes
Signing the lease before checking the pathway
The rent clock starts on the lease, not the approval. Confirm exempt, CDC or DA and the likely upgrades first.
Treating every fit-out as exempt
Partitions that change exits, services or fire separation take a fit-out out of exempt development.
Ignoring the building classification
A use that changes the NCC class is not an exempt change of use (the narrow exception is Class 5 to Class 6 or back), and it brings the new use’s fire safety requirements with it.
Assuming “permitted in the zone” means “CDC”
The LEP permits the use; the Codes SEPP decides whether it can be complying development. They are different lists.
Using the old zone names
Leases and older approvals still say B5 or IN2. Your LEP now uses E3, E4 and the other employment zones, and that is the zone the code is checked against.
Leaving fire safety to the end
Fire services, the fire safety schedule and the fire safety certificate are where commercial OCs stall. See occupation certificate delays.
Consultants who never speak
A BCA report, fire strategy and access report that describe different layouts stop the clock. See when your reports don’t talk to each other.
Changing the layout on site
A moved wall can lengthen a travel distance and put the fit-out outside its CDC. See why a minor site change can stop your project cold.
Step by step: from lease to Occupation Certificate
Confirm the pathway before you commit
Check the zone, the existing approved use, the proposed use and the NCC classification. Confirm exempt, CDC or DA with a certifier before signing a lease or exchanging.
Run a BCA and fire safety capability check
Identify upgrade triggers (exits, sanitary facilities, accessibility, fire services) and their likely cost, so the business case is real.
Design the fit-out or building to the code
Work to the Part 5 or 5A standards and the NCC from the first layout. Bring in access, fire and traffic input where triggered.
Assemble a complete CDC application
Drawings, BCA report, fire safety schedule, services design, access report, structural and traffic input as needed, and the section 10.7 certificate.
Lodge and receive the CDC
The certifier assesses against the code and the NCC and must usually determine the application within 10 days of lodgement (20 days if it includes demolition or a new dwelling near neighbours in most of metropolitan Sydney).
Appoint the Principal Certifier and build
Give the council at least 2 days’ notice before work starts. The Principal Certifier inspects at the required stages.
Fire safety certificate and Occupation Certificate
A final fire safety certificate is issued on behalf of the owner, certifying that each measure on the fire safety schedule has been assessed by an accredited practitioner (fire safety). Then the Occupation Certificate is issued and the premises can open.
How Built Smart Solutions helps
Built Smart Solutions is a Sydney-based team of registered certifiers, BCA and fire safety consultants and town planners, ISO 9001 certified, with more than 20 years in certification, fire safety and regulatory policy. For commercial and industrial clients, the value is having every discipline that decides a CDC in one team.
| You need | Built Smart service |
|---|---|
| To know if a fit-out or change of use needs approval | Exempt Development Advice |
| Eligibility review against Parts 5 and 5A, and the CDC itself | Complying Development Certificates |
| NCC compliance, change-of-use and upgrade reports | BCA Consulting |
| Fire safety strategy, schedules and audits | Fire Safety Strategy & Reports |
| Accessibility for staff and customers | Access Consulting |
| Parking, loading and traffic reports | Transport Planning |
| A DA when the CDC does not fit | DA Preparation and Planning Advice |
| Construction Certificate after a DA | Construction Certificates |
| Inspections and sign-off | Principal Certifier and Occupation Certificates |
| Portfolio or compliance strategy across multiple sites | Strategic Regulatory Guidance |
Pathway first. We confirm exempt, CDC or DA and the upgrade cost before you commit to a lease or purchase. One team. Certification, BCA, fire safety, access and traffic are coordinated in-house, so reports match and the CDC is not held up. Honest advice. When a DA is the better route, we say so and deliver it. Fixed fees, committed turnarounds and in-person inspections across Sydney and regional NSW. Meet the team · Our consultancy services.
Final verdict
Commercial and industrial complying development is one of the most useful and least understood tools in NSW planning. Since the 2022 reforms, many fit-outs, changes of use and new industrial buildings that once needed a DA can be approved by a private certifier, usually within a 10-day statutory period. The catch is that the planning pathway is only half the question. The other half is the NCC: what the new use demands of the building in exits, fire safety, accessibility and amenities.
The businesses that open on time check both before they sign. If you are leasing, buying or building commercial or industrial premises anywhere in Sydney or NSW, Built Smart Solutions will confirm your pathway, scope the upgrades and deliver the CDC, with BCA, fire, access and traffic input from the same team. Get a fee proposal or call (02) 9127 8249.
Frequently asked questions about commercial and industrial CDCs in NSW
Do I need approval for a commercial fit-out in NSW?
It depends on the work. Painting, flooring, joinery and some non-structural partitions can be exempt development. Fit-outs that change exits, travel distances, fire separation, services or structure need a Complying Development Certificate under Part 5 or 5A of the Codes SEPP, or a DA if the code does not apply. Fit-outs in heritage items need a DA.
Can I get a CDC for a commercial fit-out?
Yes, in most cases. The Industrial and Business Alterations Code (Part 5) and the Industrial and Business Buildings Code (Part 5A) of the Codes SEPP allow internal alterations and fit-outs of commercial and industrial buildings to be approved as complying development by a registered certifier, provided the land is not excluded and the work meets the code’s standards and the National Construction Code.
Do I need a DA for a change of use in NSW?
Not always. A change of use can be exempt if it is one of the listed pairings, the existing use is lawful, the new use is permissible and not on the excluded list (food and drink premises are excluded), the NCC building classification does not change (other than between Class 5 and Class 6) and no non-exempt building work is done. If it is not exempt, Part 5A of the Codes SEPP allows many changes of use to listed uses in employment zones as complying development. A DA is needed if the use is not listed for complying development, the land is excluded or the premises are a heritage item.
What is the Industrial and Business Buildings Code?
The Industrial and Business Buildings Code is Part 5A of the Codes SEPP. It allows new industrial and business buildings, additions, first use and change of use of premises, internal alterations and site works in industrial and business zones to be approved as complying development (new buildings are not covered in Zones E1, E2 or MU1), subject to development standards such as height, setbacks, landscaping, parking and loading, and operational conditions.
Can a warehouse be changed into a gym with a CDC?
Often, yes, where an indoor recreation facility is permissible in the zone, the facility is no more than 1,000 m² of gross floor area and the land is not excluded. The change is from NCC Class 7b to Class 9b, an assembly building used for recreational or sporting purposes, and for a CDC the building must have adequate egress and meet the Category 1 fire safety provisions for the new use: exits, occupant load, sanitary facilities, accessibility and fire services are commonly upgraded. A BCA change-of-use report identifies the work before lodgement.
Can a shop be turned into a café without a DA?
In many cases, yes, through a CDC under Part 5A where the use is permissible in the zone and the premises will hold no more than 100 patrons, with operating hours set by the CDC conditions. The fit-out must comply with AS 4674-2004 for food premises, and kitchen exhaust, grease arrestors, sanitary facilities and accessibility need to be designed in. A change from shop to café is not exempt development. Pubs, small bars and proposals over the patron cap need a DA.
Can I build a new warehouse without a DA?
Yes, if the site is in an industrial zone or a business zone where the code allows new buildings (not E1, E2 or MU1), the land is not excluded and the building meets every standard in Part 5A, including height, floor area, setbacks, landscaping, parking, loading and design requirements. A registered certifier can then issue a CDC. Large warehouses also need a fire safety strategy addressing compartment size, sprinklers and hydrants.
What are employment zones in NSW?
Employment zones replaced the old business and industrial zones in April 2023: E1 Local Centre, E2 Commercial Centre, E3 Productivity Support, E4 General Industrial, E5 Heavy Industrial and MU1 Mixed Use, among others. The Codes SEPP lists the new zones alongside the old names, so complying development eligibility should be checked against the zone in the current LEP.
Does a change of use trigger fire safety upgrades?
Frequently. For a CDC involving a change of building use, the building must have adequate egress from the affected part, comply with the Category 1 fire safety provisions for the new use, and have fire protection and structural capacity appropriate to it. That can mean additional exits, revised travel distances, fire services, emergency lighting, a revised fire safety schedule and a fire safety certificate before the Occupation Certificate.
How long does a commercial CDC take?
The Regulation usually requires a commercial or industrial CDC to be determined within 10 days of lodgement, unless the applicant agrees to a longer period. The period is 20 days where the application includes demolition under the Demolition Code, or a new dwelling, on a lot in most of metropolitan Sydney within 20 m of a lot with a dwelling. Including design, BCA and fire input, most fit-outs and changes of use go from concept to CDC in a matter of weeks, compared with several months for a commercial DA plus a Construction Certificate.
How much does a commercial CDC cost in Sydney?
There is no list price, and a range quoted without a scope behind it is not much use. The fee for the CDC, Principal Certifier, inspections and Occupation Certificate is set by the building class, the size of the works, any change of BCA classification, the fire safety measures involved and the number of inspections. BCA, fire, access and traffic input is additional where the project needs it. Built Smart Solutions quotes a fixed fee against a written scope.
Who is responsible for the approval: the landlord or the tenant?
Usually the tenant applies for approval of their fit-out or change of use with the landlord’s written consent as owner, but lease terms vary. The statutory duties to maintain essential fire safety measures, keep the servicing records and give the annual fire safety statement sit on the building owner, and a lease cannot transfer them, although it can allocate who does the work and who pays. Clarify responsibilities, including who pays for base-building upgrades, before signing.
What happens if I open without an Occupation Certificate?
Occupying or using a building, or part of one, without an Occupation Certificate where one is required is an offence and can lead to council orders, penalties and insurance problems. For commercial premises, the OC depends on the fire safety certificate for every measure on the fire safety schedule, so fire services should be programmed early.
Can heritage-listed commercial buildings use a CDC?
Generally no. Complying development is not available on land that is, or contains, a listed heritage item, apart from limited Heritage Act exemptions, so fit-outs, changes of use and alterations to heritage items usually need a development application with a heritage impact statement. In heritage conservation areas, Part 5A allows only change of use and internal alterations, while Part 5 internal alterations remain available.
Does Built Smart Solutions handle commercial and industrial CDCs?
Yes. Built Smart Solutions confirms the pathway, issues commercial and industrial CDCs as registered certifiers, acts as Principal Certifier and issues Occupation Certificates, with BCA, fire safety, access and traffic input from the same team, across Sydney and regional NSW. When a DA is the better route, our town planning team prepares and manages it.
Tell us about your tenancy or building.
Pathway check, CDC, BCA, fire safety, access and traffic input, inspections and the Occupation Certificate, from one Sydney team on a fixed fee. ISO 9001 certified.
Related reading from Built Smart Insights
This guide reflects the Codes SEPP (including Parts 2, 5 and 5A), the employment zones and the NCC as at October 2026 and is general information only. Lists of uses permitted as exempt or complying development, development standards and land exclusions vary by zone and site; worked examples are composites. Nothing in this article is advice about a particular property or tenancy. For a fixed fee, request a fee proposal.
Built Smart Solutions. Get Your Project Approved. Keep Your Building Compliant.