Commercial and Industrial CDCs in NSW: Fit-Outs, Change of Use and New Warehouses Without a DA

Most writing about complying development is about houses. This guide is about the other half: shop and office fit-outs, cafés, gyms, warehouses, factories and business parks. It explains when commercial work is exempt, when it can be approved by a CDC under the Industrial and Business Codes in weeks, when it needs a DA, and the BCA and fire safety triggers that decide whether a “simple” fit-out or change of use stays simple. Written by the registered certifiers at Built Smart Solutions in Sydney.

SEO/AI under the hood (amended per review actions 2 & R4): exact-match H1 restored per audit 2.1 – the personality line survives as the subhead · URL /services/certification/ per the audit keyword map · meta description: “Principal Certifier Appointment, Construction & Occupation Certificates and Complying Development (CDC) from one specialist, ISO 9001-certified team – approval to occupation.” (adopted from Option 1’s written set) · the “Quick Answer” block is deliberately extractable – it’s the sentence we want ChatGPT/Gemini/AI Overviews to quote · FAQPage + Service schema · 800+ words at full build · division-coded breadcrumb.

Quick answer

In NSW, commercial and industrial work can follow three pathways. Exempt development needs no approval: some non-structural internal fit-outs, and a listed change of use where the existing use is lawful, the new use is permissible and not on the excluded list (food and drink premises are excluded), the NCC building classification does not change (other than between Class 5 and Class 6) and no non-exempt building work is done. Complying development covers larger internal alterations, changes of use, new industrial and business buildings and additions that meet the standards in the Codes SEPP Part 5 (Industrial and Business Alterations Code) and Part 5A (Industrial and Business Buildings Code). A registered certifier or council must usually determine a commercial or industrial CDC within 10 days; the period is 20 days if the application includes demolition under the Demolition Code, or a new dwelling such as a caretaker’s flat, on a lot in most of metropolitan Sydney within 20 m of a lot with a dwelling. Anything that falls outside those codes, or sits on excluded land, needs a development application.

Whatever the pathway, the building must comply with the National Construction Code for the use, so changes of use and fit-outs often trigger fire safety, egress and accessibility upgrades. The certification fee is set by the scope, not a list price: the building class, the size of the works, any change of BCA classification, the fire safety measures involved and the number of inspections, plus BCA and fire safety input where needed. Built Smart Solutions confirms the pathway, issues commercial and industrial CDCs as registered certifiers, and brings BCA, fire safety, access and traffic advice into one team.

Key takeaways

  • Three pathways, not two. Some commercial fit-outs and changes of use are exempt, many are CDC, the rest are DA. Check in that order.
  • The building classification is the hinge. If the new use changes the NCC class (for example a warehouse becoming a gym), the change of use is not exempt (the only exception is between Class 5 and Class 6), and for a CDC the building must meet the Category 1 fire safety provisions for the new use.
  • Two codes do most of the work: Part 5 (Industrial and Business Alterations Code) for alterations, and Part 5A (Industrial and Business Buildings Code) for new buildings, additions, change of use and site works.
  • Zones were renamed in 2023. The old B and IN zones became employment zones E1 to E5 and MU1. The codes list the new names alongside the old ones; your LEP uses the new ones.
  • Fire safety decides the budget. Egress, fire separation, sprinklers, hydrants and the fire safety schedule are where commercial CDCs succeed or stall.
  • Lease last, pathway first. Confirm the approval pathway and upgrade cost before signing a lease or buying a building.
  • One team helps. Built Smart Solutions handles the certification, BCA, fire safety, access and traffic input in-house, so the CDC is not held up waiting on consultants who never spoke to each other.

Exempt, CDC or DA: the three pathways for commercial work

The State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 (the Codes SEPP) sets two of the three pathways; the third is a development application under the Environmental Planning and Assessment Act 1979. Our CDC vs DA guide covers the general decision; this table shows how it plays out for commercial and industrial work.

Approval pathways for commercial and industrial work in NSW (2026)
PathwayTypical commercial workWho approvesTimeframeKey condition
Exempt developmentNon-structural internal fit-outs; listed changes of use with no change in NCC classification (other than Class 5 to Class 6 or back) and no non-exempt building workNo approvalImmediateEvery exempt standard met; existing use lawful
Complying development (CDC)Internal alterations, shopfronts, change of use, first use, new industrial and business buildings, additions, site and parking upgradesRegistered certifier or councilUsually a 10-day statutory determination period on a complete applicationEvery standard in Part 5 or 5A met; land not excluded
Development application (DA)Anything outside the codes: excluded land, non-listed uses, larger or non-compliant buildings, heritage items, hazardous or offensive industryConsent authority (usually the council or a planning panel)Commonly several months for commercial work in Sydney, plus a Construction CertificateMerit assessment
Watch for this

“Exempt” is the most misused word in commercial leasing. An agent’s “you don’t need approval, it’s just a fit-out” is not advice. If the work touches structure, fire safety, egress, services or the building classification, it is almost certainly not exempt. Get exempt development advice in writing before you rely on it.

The Industrial and Business Codes explained

Commercial and industrial complying development sits mainly in two parts of the Codes SEPP, which were expanded by the Building Business Back Better reforms that commenced on 1 February 2022, and were later updated to refer to the employment zones.

Codes SEPP provisions for commercial and industrial development in NSW
ProvisionWhat it coversTypical projects
Part 2, Subdivision 10A (exempt)Change of use of premises as exempt development, subject to strict conditionsListed pairings, such as shop, office and business premises to one another, or light industry to warehouse, with no non-exempt works
Part 2 (other exempt subdivisions)Minor non-structural internal alterations, signage and minor worksPainting, joinery, carpets, non-structural partitions that do not affect fire safety or egress
Part 5: Industrial and Business Alterations CodeInternal alterations that do not increase gross floor area, shopfronts and awnings, mechanical ventilation, signs and other minor works to existing buildingsOffice and retail fit-outs, shopfront replacement, internal reconfiguration
Part 5A: Industrial and Business Buildings CodeNew industrial and business buildings, additions, first use and change of use of premises, internal alterations, site works and parkingNew warehouses and factories, extensions, warehouse to gym, shop to café, office to health consulting rooms or a medical centre
Part 8: Fire Safety CodeCertain fire safety upgrades to existing buildingsUpgrades required following an audit or order
Part 7: Demolition CodeDemolition of non-excluded buildingsStrip-outs and demolition ahead of a new building

Within Part 5A, the zone-specific building standards (height, setbacks, landscaping and the like) apply only where the development involves building work, and not to internal alterations that do not increase gross floor area. A change of use still has to meet the general standards that apply to every Part 5A development, including parking, any new loading or driveway works, and the caps for particular uses, and the building still has to meet the fire safety requirements for the new use. Part 5A also covers only listed purposes, its “specified purposes”, and excludes others outright, including pubs, small bars, registered clubs and potentially hazardous or offensive industries. New buildings are not covered in Zones E1, E2 or MU1. So the first check is always whether your proposed use and zone are covered.

Employment zones: E1 to E5, MU1 and what they allow

In April 2023 NSW replaced the old business (B) and industrial (IN) zones with employment zones. Leases, older approvals and many websites still use the old names, which causes confusion. The Codes SEPP lists both the new and the old names.

NSW employment zones and the zones they replaced
New zoneNameBroadly replacedTypical uses
E1Local CentreB1 Neighbourhood Centre, B2 Local CentreShops, cafés, services, small offices, shop-top housing
E2Commercial CentreB3 Commercial CoreOffices, retail, entertainment in major centres
E3Productivity SupportB5 Business Development, B6 Enterprise Corridor, B7 Business Park and some IN2Bulky goods, light industry, creative industries, offices, gyms, trade supplies
E4General IndustrialIN1 General Industrial, IN2 Light IndustrialWarehouses, factories, depots, logistics
E5Heavy IndustrialIN3 Heavy IndustrialHeavy and hazardous industry (often outside CDC)
MU1Mixed UseB4 Mixed UseRetail and commercial with residential above

Zone permissibility comes from the council’s LEP; the Codes SEPP then says which of those permitted uses can be approved as complying development. A use can be permitted in the zone and still need a DA because the code does not list it. A planner or certifier confirms both from the LEP and the section 10.7 certificate.

Fit-outs: when they are exempt and when they need a CDC

A fit-out is not a legal category; it is a description of work. Whether it needs approval depends on what the work touches.

Commercial fit-out approval in NSW: exempt vs CDC vs DA
Fit-out workLikely pathwayWhy
Painting, flooring, joinery, furniture, loose fittingsExemptNo structure, services or fire safety affected
Non-structural partitions that do not change exits, travel distances or fire separationOften exemptSubject to the exempt standards; egress must not be affected
New partitions that change exit paths, travel distances or room layoutsCDC (Part 5 or 5A)Egress and fire safety must be reassessed against the NCC
New or relocated amenities, kitchens, plumbing and mechanical servicesCDCServices and NCC health and amenity provisions
Structural work, mezzanines, openings in walls or floorsCDC under Part 5A (within its limits) or DA; Part 5 does not allow added floor area, other than to meet the Premises StandardsStructure, fire separation and floor area
Shopfront replacementCDC, sometimes exemptDepends on the code standards and heritage
Fit-out in a heritage itemDAHeritage items are excluded from complying development, apart from limited Heritage Act exemptions
Fit-out combined with a change of use that changes NCC classCDC or DANot exempt; for a CDC the building must meet the Category 1 fire safety provisions for the new use

The trigger most people miss is egress. A fit-out that subdivides a tenancy, adds meeting rooms or closes a corridor can push travel distances to an exit beyond the NCC limits, or leave a room with only one exit where two are required. Our BCA consultant guide explains why fit-outs are the most common way a compliant building becomes non-compliant.

Change of use: exempt, CDC or DA

A change of use happens when premises start being used for a different purpose: a warehouse becomes a gym, a shop becomes a café, an office becomes a clinic, a factory becomes a self-storage facility. It needs approval even if no building work is done, unless it qualifies as exempt.

When a change of use is exempt

Under Part 2, Subdivision 10A of the Codes SEPP, a change of use can be exempt development only if it is one of the listed pairings (for example shop to office, office to business premises, or light industry to warehouse) and every standard is met: the existing use is lawful and does not rely on existing use rights; the new use is permissible with consent; the building’s classification does not change, other than between Class 5 and Class 6 where the building meets the code for the new use; the new use is not on the excluded list, which includes food and drink premises, hair and beauty salons and skin penetration premises; no building work is carried out other than exempt work; gross floor area does not increase; and existing consent conditions on matters such as parking, traffic and waste, and in some zones hours, are not breached.

When a change of use can be a CDC

Where a change of use is not exempt, Part 5A allows first use and change of use of premises to specified uses in specified zones as complying development, subject to the code’s requirements. Typical CDC changes of use in Sydney include warehouses to gyms or indoor recreation, light industrial units to creative industries or trade showrooms, and vacant shops to food and drink premises. Watch the caps: indoor recreation facilities such as gyms are limited to 1,000 m² of gross floor area, and food and drink premises to 100 patrons.

When a change of use needs a DA

A DA is needed when the new use is not listed for complying development in that zone, the land is excluded, the premises are a heritage item, or the use falls into a category the code excludes (for example hazardous or offensive industry). Childcare centres, places of public worship, pubs, small bars and registered clubs fall here, because they are not specified purposes under Part 5A. Health consulting rooms and medical centres, by contrast, are specified purposes and can be complying development where permissible.

Common Sydney changes of use and their likely approval pathway
FromToNCC class changeLikely pathwayTypical upgrade triggers
ShopShop (different retailer)None (Class 6 to 6)Often exemptNone if no works
OfficeOfficeNone (Class 5 to 5)Often exemptNone if no works
WarehouseGym / indoor recreationClass 7b to Class 9b (assembly building for recreational or sporting purposes)CDC (Part 5A) where permissible and no more than 1,000 m², else DAOccupant load, exits, sanitary facilities, accessibility, fire services
ShopCafé or restaurantClass 6 to Class 6, higher occupant loadCDC (Part 5A) up to 100 patrons, else DAExhaust, grease trap, sanitary facilities, patron cap, operating hours
FactoryWarehouse / storageClass 8 to Class 7bCDC (Part 5A)Fire compartment size, sprinklers, hydrant coverage
OfficeMedical or health consultingClass 5 to Class 5 or 9a depending on servicesCDC (Part 5A) where permissible, else DAAccessibility, sanitary facilities, sometimes health care class provisions
CommercialChildcareTo Class 9bDAWhole-of-building fire, egress, access, acoustic

Our fire safety consultant guide explains why changes of use are where fire safety upgrades most often appear.

New warehouses, factories and additions

Part 5A allows new industrial and business buildings and additions to existing ones to be approved as complying development in industrial zones and some business zones (new buildings are not covered in Zones E1, E2 or MU1), provided every development standard is met. In industrial zones the code now allows buildings of up to 50,000 m² of gross floor area, and the standards cover, among other things:

  • Building height and gross floor area limits for the zone and lot.
  • Setbacks to the street, side and rear boundaries, with greater setbacks and interface controls where the site adjoins a residential zone.
  • Landscaping to the street frontage and boundaries.
  • Car parking, loading and vehicle access, including manoeuvring for the design vehicle.
  • Stormwater, earthworks and retaining walls.
  • External finishes and design requirements, including a design statement by a qualified designer for buildings in Zone E3 and the former B5 to B7 zones.
  • Hours of operation, set by the CDC conditions where no existing consent condition applies, and other operational conditions for the use.

New warehouses and factories also bring in the full weight of NCC Volume One: fire compartment sizes, sprinkler and hydrant requirements, smoke hazard management, egress for large floor plates, and accessibility to offices and amenities. For a large-volume building, the BCA and fire strategy usually drive the design more than the planning standards. Our Western Sydney industrial and office case study shows how an early BCA upgrade and fire safety strategy kept a project on track.

Parking and loading are the planning standards new industrial buildings most often miss. Where the design cannot meet them, or council’s traffic engineer will need convincing on a DA, a traffic and parking assessment resolves it before lodgement.

BCA and fire safety triggers: where commercial CDCs stall

The planning standards decide whether a commercial project can be a CDC. The National Construction Code decides what it costs. These are the triggers that turn a “simple” fit-out or change of use into a building upgrade.

BCA and fire safety triggers for commercial fit-outs and changes of use in NSW
TriggerWhat it meansTypical consequenceWho resolves it
Change of NCC classificationThe new use is a different class (for example 7b to 9b)For a CDC, the building must have adequate egress and comply with the Category 1 fire safety provisions for the new use, with fire protection and structural capacity suited to it; upgrades likelyBCA consultant and certifier
Higher occupant loadMore people (gyms, cafés, assembly uses)More or wider exits, more sanitary facilities, travel distance checksBCA consultant
Travel distance and exitsNew partitions lengthen paths to exitsLayout changes or a performance solutionBCA consultant; fire engineer if needed
Fire compartment sizeLarge open floors, especially warehousesSprinklers, fire walls or a performance solutionFire safety consultant
Fire servicesHydrant and hose reel coverage, detection, emergency lighting, exit signsNew or extended services and a revised fire safety scheduleFire safety consultant and services contractor
AccessibilityAccess to and within the building, accessible sanitary facilitiesRamps, lifts, accessible toilets, or a justified departureAccess consultant
Fire safety schedule and certificateMeasures listed on the schedule must be installed and certifiedFire safety certificate before the OC; annual statements thereafterCertifier, accredited practitioner
Existing non-compliancesProblems already in the building are uncoveredOn a change of use that changes the NCC class, the Category 1 fire safety provisions apply to the new use regardless; on alterations, fire protection and structural capacity must not be reduced, and a reconfigured part must have adequate egressBCA consultant and certifier
Pro tip

Ask for a short BCA and fire safety capability check before you sign a lease or exchange on a commercial building. It costs a fraction of one month’s rent and tells you whether the use you want needs a minor fit-out or a five-figure upgrade. Built Smart Solutions runs these as part of every commercial CDC fee proposal.

After the Occupation Certificate, the building owner carries ongoing obligations: maintaining every essential fire safety measure, having it inspected, tested and serviced to AS 1851-2012 where that standard addresses the activity (emergency and exit lighting sits under AS/NZS 2293), keeping the records on site for at least 7 years, and giving an annual fire safety statement. Our articles on annual fire safety statements and the 2026 fire safety reforms explain what that means for tenants and owners.

When a commercial CDC is not available

  • Heritage items, apart from limited Heritage Act exemptions.
  • Land excluded for the Industrial and Business Buildings Code, including heritage conservation areas, environmentally sensitive land and significantly contaminated land: new buildings and additions are excluded there, but a change of use or internal alterations can still be complying development.
  • Environmentally sensitive areas and other land excluded for all complying development.
  • BAL-40 and Flame Zone land, and flood or bushfire land that does not meet the code’s standards.
  • Uses not listed for complying development in the zone, even if the LEP permits them.
  • Hazardous or offensive industry, designated development and uses needing approvals the code excludes.
  • Buildings or extensions beyond the code’s height, floor area or setback standards.
  • Unapproved existing works or uses. A certifier cannot build on an unlawful starting point; it may need regularising first.
  • Land subject to a restriction or a site-specific exclusion stated on the section 10.7 planning certificate.

When a CDC is not available, a well-prepared DA is the route. Built Smart Solutions’ town planning team handles commercial DA preparation and the Statement of Environmental Effects, including the staff numbers, hours, access, loading and waste details councils expect for a change of use.

Worked examples from Sydney projects

These composite examples reflect the kinds of commercial and industrial projects we see across Sydney. Details are generalised.

Commercial and industrial CDC examples in Sydney
ProjectPathwayWhat decided itOutcome
Office tenancy refresh, open plan to meeting rooms, ParramattaCDC (Part 5)New partitions changed exit pathsLayout adjusted to keep travel distances compliant; CDC issued without a performance solution
Warehouse unit to boutique gym, Western Sydney (E4)CDC (Part 5A)Use covered in the zone and under the 1,000 m² cap; class change from 7b to 9bAdditional exit, accessible toilet and emergency lighting added; CDC issued
Vacant shop to café, Inner West (E1)CDC (Part 5A)Patron numbers within the code’s 100-patron capExhaust, grease arrestor and sanitary facilities designed in; CDC issued
Retail to medical consulting rooms, North ShoreDAUse not suited to the CDC pathway at that siteDA with access and parking reports
New 8,000 m² warehouse, South West Sydney (E4)CDC (Part 5A)Height, setbacks, landscaping and parking metFire strategy with sprinklers set early; CDC issued, partial occupation certificate for the first stage
Shop fit-out in a heritage-listed building, CBDDAHeritage item excludedDA with heritage impact statement, then CC

Commercial CDC costs, and what actually moves the number

Commercial and industrial certification is scoped work, not a list price. Two fit-outs of the same floor area can carry very different fees once the building class, the fire safety measures and the specialist input are known, and a range quoted without that scope tells you very little. What follows is what sets the fee, and what a proposal has to state before you can compare one to another. Construction is excluded.

What sets the approval cost for commercial and industrial projects in NSW
FactorWhy it moves the fee
The pathwayExempt work needs no certificate. A CDC is assessed by the certifier as one certificate. A DA adds the council’s fee, a Statement of Environmental Effects and a separate Construction Certificate, and months of holding cost.
Use and building classA change of use that changes the building’s BCA classification brings in the Regulation’s fire safety upgrade provisions, which widens the BCA and fire safety scope.
Size and type of workFloor area, storeys and whether the work is a fit-out, an addition or a new building set the assessment and inspection effort.
Fire safety measuresNew or altered essential fire safety measures need design, certification and a fire safety schedule, and often a fire engineer.
AccessWork affecting the path of travel can trigger access upgrades under the NCC and the Premises Standards, and an access report to support them.
Traffic and parkingNew warehouses and some changes of use need traffic, parking and loading input.
InspectionsThe critical stage inspections are set by the Regulation for the class of building and the work.
Contributions, Long Service Levy and government feesContributions apply where the council’s plan provides for them. The Long Service Levy is 0.25% of the cost of works of $250,000 or more. Lodgement, certificate and agency fees are set by government and change from time to time, so a proposal should list them as pass-through items rather than build them into the fee.

What a comparable proposal has to tell you

  • The BCA classification before and after. And whether the change brings in the fire safety upgrade provisions.
  • Which code, or why not. The Codes SEPP part relied on, or the reason the work needs a DA or is exempt.
  • What the fee covers. The CDC, the Principal Certifier appointment, each critical stage inspection, the fire safety certificate process and the Occupation Certificate.
  • What it excludes. BCA, fire, access and traffic reports, contributions, the Long Service Levy and government fees, stated as excluded rather than simply left out.
  • The turnaround. When the CDC will be determined once the application is complete, and the inspection notice period.
  • A fixed fee against that scope, rather than an hourly rate with no cap.

Built Smart Solutions quotes every engagement as a fixed fee against a written scope, with the exclusions and the turnaround stated on the same page. Get a fee proposal.

For a commercial tenant, the biggest cost is rarely the approval fee. It is rent on a tenancy that cannot open. A CDC instead of a three-month DA can be worth more than the whole approval budget.

3Pathways for commercial work: exempt, CDC, DA
10 daysUsual statutory determination period for a commercial or industrial CDC
1 Feb 2022Building Business Back Better reforms expanded commercial and industrial CDCs
E1 to E5, MU1Employment zones that replaced the B and IN zones in 2023

Timelines: CDC vs DA for commercial projects

Commercial project timelines in Sydney: CDC vs DA (2026)
StageCDCDA + CC
Pathway and capability checkA few daysA few days
Design, BCA and fire inputUsually a few weeksUsually longer, plus the SoEE and reports
AssessmentUsually a 10-day statutory period on a complete applicationCommonly several months, and longer for a new building
Construction approvalIncludedA separate Construction Certificate after consent
Fit-out works and inspectionsProject-dependentProject-dependent
Fire safety certificate and OCOnce the works are complete and the final fire safety certificate is inOnce the works are complete and the final fire safety certificate is in

About to sign a lease or buy a building?

Tell us the address and the use. Built Smart Solutions will confirm whether it is exempt, CDC or DA and what upgrades to expect, before you commit.

Common mistakes

Signing the lease before checking the pathway

The rent clock starts on the lease, not the approval. Confirm exempt, CDC or DA and the likely upgrades first.

Treating every fit-out as exempt

Partitions that change exits, services or fire separation take a fit-out out of exempt development.

Ignoring the building classification

A use that changes the NCC class is not an exempt change of use (the narrow exception is Class 5 to Class 6 or back), and it brings the new use’s fire safety requirements with it.

Assuming “permitted in the zone” means “CDC”

The LEP permits the use; the Codes SEPP decides whether it can be complying development. They are different lists.

Using the old zone names

Leases and older approvals still say B5 or IN2. Your LEP now uses E3, E4 and the other employment zones, and that is the zone the code is checked against.

Leaving fire safety to the end

Fire services, the fire safety schedule and the fire safety certificate are where commercial OCs stall. See occupation certificate delays.

Consultants who never speak

A BCA report, fire strategy and access report that describe different layouts stop the clock. See when your reports don’t talk to each other.

Changing the layout on site

A moved wall can lengthen a travel distance and put the fit-out outside its CDC. See why a minor site change can stop your project cold.

Step by step: from lease to Occupation Certificate

  1. Confirm the pathway before you commit

    Check the zone, the existing approved use, the proposed use and the NCC classification. Confirm exempt, CDC or DA with a certifier before signing a lease or exchanging.

  2. Run a BCA and fire safety capability check

    Identify upgrade triggers (exits, sanitary facilities, accessibility, fire services) and their likely cost, so the business case is real.

  3. Design the fit-out or building to the code

    Work to the Part 5 or 5A standards and the NCC from the first layout. Bring in access, fire and traffic input where triggered.

  4. Assemble a complete CDC application

    Drawings, BCA report, fire safety schedule, services design, access report, structural and traffic input as needed, and the section 10.7 certificate.

  5. Lodge and receive the CDC

    The certifier assesses against the code and the NCC and must usually determine the application within 10 days of lodgement (20 days if it includes demolition or a new dwelling near neighbours in most of metropolitan Sydney).

  6. Appoint the Principal Certifier and build

    Give the council at least 2 days’ notice before work starts. The Principal Certifier inspects at the required stages.

  7. Fire safety certificate and Occupation Certificate

    A final fire safety certificate is issued on behalf of the owner, certifying that each measure on the fire safety schedule has been assessed by an accredited practitioner (fire safety). Then the Occupation Certificate is issued and the premises can open.

How Built Smart Solutions helps

Built Smart Solutions is a Sydney-based team of registered certifiers, BCA and fire safety consultants and town planners, ISO 9001 certified, with more than 20 years in certification, fire safety and regulatory policy. For commercial and industrial clients, the value is having every discipline that decides a CDC in one team.

Built Smart Solutions services for commercial and industrial projects
You needBuilt Smart service
To know if a fit-out or change of use needs approvalExempt Development Advice
Eligibility review against Parts 5 and 5A, and the CDC itselfComplying Development Certificates
NCC compliance, change-of-use and upgrade reportsBCA Consulting
Fire safety strategy, schedules and auditsFire Safety Strategy & Reports
Accessibility for staff and customersAccess Consulting
Parking, loading and traffic reportsTransport Planning
A DA when the CDC does not fitDA Preparation and Planning Advice
Construction Certificate after a DAConstruction Certificates
Inspections and sign-offPrincipal Certifier and Occupation Certificates
Portfolio or compliance strategy across multiple sitesStrategic Regulatory Guidance
Why commercial clients use Built Smart

Pathway first. We confirm exempt, CDC or DA and the upgrade cost before you commit to a lease or purchase. One team. Certification, BCA, fire safety, access and traffic are coordinated in-house, so reports match and the CDC is not held up. Honest advice. When a DA is the better route, we say so and deliver it. Fixed fees, committed turnarounds and in-person inspections across Sydney and regional NSW. Meet the team · Our consultancy services.

Final verdict

Commercial and industrial complying development is one of the most useful and least understood tools in NSW planning. Since the 2022 reforms, many fit-outs, changes of use and new industrial buildings that once needed a DA can be approved by a private certifier, usually within a 10-day statutory period. The catch is that the planning pathway is only half the question. The other half is the NCC: what the new use demands of the building in exits, fire safety, accessibility and amenities.

The businesses that open on time check both before they sign. If you are leasing, buying or building commercial or industrial premises anywhere in Sydney or NSW, Built Smart Solutions will confirm your pathway, scope the upgrades and deliver the CDC, with BCA, fire, access and traffic input from the same team. Get a fee proposal or call (02) 9127 8249.

Frequently asked questions about commercial and industrial CDCs in NSW

Do I need approval for a commercial fit-out in NSW?

It depends on the work. Painting, flooring, joinery and some non-structural partitions can be exempt development. Fit-outs that change exits, travel distances, fire separation, services or structure need a Complying Development Certificate under Part 5 or 5A of the Codes SEPP, or a DA if the code does not apply. Fit-outs in heritage items need a DA.

Can I get a CDC for a commercial fit-out?

Yes, in most cases. The Industrial and Business Alterations Code (Part 5) and the Industrial and Business Buildings Code (Part 5A) of the Codes SEPP allow internal alterations and fit-outs of commercial and industrial buildings to be approved as complying development by a registered certifier, provided the land is not excluded and the work meets the code’s standards and the National Construction Code.

Do I need a DA for a change of use in NSW?

Not always. A change of use can be exempt if it is one of the listed pairings, the existing use is lawful, the new use is permissible and not on the excluded list (food and drink premises are excluded), the NCC building classification does not change (other than between Class 5 and Class 6) and no non-exempt building work is done. If it is not exempt, Part 5A of the Codes SEPP allows many changes of use to listed uses in employment zones as complying development. A DA is needed if the use is not listed for complying development, the land is excluded or the premises are a heritage item.

What is the Industrial and Business Buildings Code?

The Industrial and Business Buildings Code is Part 5A of the Codes SEPP. It allows new industrial and business buildings, additions, first use and change of use of premises, internal alterations and site works in industrial and business zones to be approved as complying development (new buildings are not covered in Zones E1, E2 or MU1), subject to development standards such as height, setbacks, landscaping, parking and loading, and operational conditions.

Can a warehouse be changed into a gym with a CDC?

Often, yes, where an indoor recreation facility is permissible in the zone, the facility is no more than 1,000 m² of gross floor area and the land is not excluded. The change is from NCC Class 7b to Class 9b, an assembly building used for recreational or sporting purposes, and for a CDC the building must have adequate egress and meet the Category 1 fire safety provisions for the new use: exits, occupant load, sanitary facilities, accessibility and fire services are commonly upgraded. A BCA change-of-use report identifies the work before lodgement.

Can a shop be turned into a café without a DA?

In many cases, yes, through a CDC under Part 5A where the use is permissible in the zone and the premises will hold no more than 100 patrons, with operating hours set by the CDC conditions. The fit-out must comply with AS 4674-2004 for food premises, and kitchen exhaust, grease arrestors, sanitary facilities and accessibility need to be designed in. A change from shop to café is not exempt development. Pubs, small bars and proposals over the patron cap need a DA.

Can I build a new warehouse without a DA?

Yes, if the site is in an industrial zone or a business zone where the code allows new buildings (not E1, E2 or MU1), the land is not excluded and the building meets every standard in Part 5A, including height, floor area, setbacks, landscaping, parking, loading and design requirements. A registered certifier can then issue a CDC. Large warehouses also need a fire safety strategy addressing compartment size, sprinklers and hydrants.

What are employment zones in NSW?

Employment zones replaced the old business and industrial zones in April 2023: E1 Local Centre, E2 Commercial Centre, E3 Productivity Support, E4 General Industrial, E5 Heavy Industrial and MU1 Mixed Use, among others. The Codes SEPP lists the new zones alongside the old names, so complying development eligibility should be checked against the zone in the current LEP.

Does a change of use trigger fire safety upgrades?

Frequently. For a CDC involving a change of building use, the building must have adequate egress from the affected part, comply with the Category 1 fire safety provisions for the new use, and have fire protection and structural capacity appropriate to it. That can mean additional exits, revised travel distances, fire services, emergency lighting, a revised fire safety schedule and a fire safety certificate before the Occupation Certificate.

How long does a commercial CDC take?

The Regulation usually requires a commercial or industrial CDC to be determined within 10 days of lodgement, unless the applicant agrees to a longer period. The period is 20 days where the application includes demolition under the Demolition Code, or a new dwelling, on a lot in most of metropolitan Sydney within 20 m of a lot with a dwelling. Including design, BCA and fire input, most fit-outs and changes of use go from concept to CDC in a matter of weeks, compared with several months for a commercial DA plus a Construction Certificate.

How much does a commercial CDC cost in Sydney?

There is no list price, and a range quoted without a scope behind it is not much use. The fee for the CDC, Principal Certifier, inspections and Occupation Certificate is set by the building class, the size of the works, any change of BCA classification, the fire safety measures involved and the number of inspections. BCA, fire, access and traffic input is additional where the project needs it. Built Smart Solutions quotes a fixed fee against a written scope.

Who is responsible for the approval: the landlord or the tenant?

Usually the tenant applies for approval of their fit-out or change of use with the landlord’s written consent as owner, but lease terms vary. The statutory duties to maintain essential fire safety measures, keep the servicing records and give the annual fire safety statement sit on the building owner, and a lease cannot transfer them, although it can allocate who does the work and who pays. Clarify responsibilities, including who pays for base-building upgrades, before signing.

What happens if I open without an Occupation Certificate?

Occupying or using a building, or part of one, without an Occupation Certificate where one is required is an offence and can lead to council orders, penalties and insurance problems. For commercial premises, the OC depends on the fire safety certificate for every measure on the fire safety schedule, so fire services should be programmed early.

Can heritage-listed commercial buildings use a CDC?

Generally no. Complying development is not available on land that is, or contains, a listed heritage item, apart from limited Heritage Act exemptions, so fit-outs, changes of use and alterations to heritage items usually need a development application with a heritage impact statement. In heritage conservation areas, Part 5A allows only change of use and internal alterations, while Part 5 internal alterations remain available.

Does Built Smart Solutions handle commercial and industrial CDCs?

Yes. Built Smart Solutions confirms the pathway, issues commercial and industrial CDCs as registered certifiers, acts as Principal Certifier and issues Occupation Certificates, with BCA, fire safety, access and traffic input from the same team, across Sydney and regional NSW. When a DA is the better route, our town planning team prepares and manages it.

Tell us about your tenancy or building.

Pathway check, CDC, BCA, fire safety, access and traffic input, inspections and the Occupation Certificate, from one Sydney team on a fixed fee. ISO 9001 certified.

Written by the Built Smart Solutions certification and consultancy team, Sydney

Registered certifiers, BCA and fire safety consultants and town planners based in Sydney and working across NSW, with more than 20 years in certification, fire safety and regulatory policy, including private development and Crown building work. Registered under the Building and Development Certifiers Act 2018 (NSW), ISO 9001:2015 certified, members of the Association of Australian Certifiers. Meet the team · Certification · All services · FAQ

This guide reflects the Codes SEPP (including Parts 2, 5 and 5A), the employment zones and the NCC as at October 2026 and is general information only. Lists of uses permitted as exempt or complying development, development standards and land exclusions vary by zone and site; worked examples are composites. Nothing in this article is advice about a particular property or tenancy. For a fixed fee, request a fee proposal.