What Happens When Your Building Doesn’t Meet the National Construction Code? Your Options Explained

Home / Insights / When a building doesn’t meet the NCC

Regulation Decoded

What Happens When Your Building Doesn’t Meet the National Construction Code? Your Options Explained

Non-compliance, defect or serious defect: what each means, the four ways forward in NSW, what certifiers and regulators can do, your rights as an owner, and the steps to take when a building does not comply.

SEO/AI under the hood (amended per review actions 2 & R4): exact-match H1 restored per audit 2.1 – the personality line survives as the subhead · URL /services/certification/ per the audit keyword map · meta description: “Principal Certifier Appointment, Construction & Occupation Certificates and Complying Development (CDC) from one specialist, ISO 9001-certified team – approval to occupation.” (adopted from Option 1’s written set) · the “Quick Answer” block is deliberately extractable – it’s the sentence we want ChatGPT/Gemini/AI Overviews to quote · FAQPage + Service schema · 800+ words at full build · division-coded breadcrumb.

Quick answer

When a building does not meet the National Construction Code (NCC) in NSW, there are four main ways forward: rectify the work so it complies with the Deemed-to-Satisfy Provisions; show it meets the NCC Performance Requirements through a Performance Solution; modify the approval where the change is acceptable and can lawfully be approved; or, where the builder or developer will not fix it, use the regulatory and dispute routes available through Building Commission NSW, council, NCAT and the courts. The Principal Certifier cannot issue an Occupation Certificate unless the work is consistent with the development consent and the building is suitable for occupation for its classification.

The right option depends on when the non-compliance is found, how serious it is, the building class and who is responsible. Built Smart Solutions, a Sydney-based building certification and construction regulation firm, provides BCA assessments, Performance Solution advice and expert witness services for owners, developers and owners corporations across Sydney and NSW.

Key takeaways

  • Not every non-compliance is a defect, and not every defect is serious. The category decides who can act and how.
  • Found early is easier to fix. Non-compliances picked up at inspection are far easier to resolve than ones found after occupation.
  • A certifier cannot approve non-compliant work. The work must be fixed, justified by a Performance Solution, or the approval lawfully modified.
  • Performance Solutions can avoid demolition where the as-built work can be shown to meet the Performance Requirements.
  • Apartments have extra protection. For Class 2 buildings and certain Class 3 and 9c buildings, rectification, prohibition and stop work orders are available, administered by Building Commission NSW.
  • Owners have statutory rights, including Home Building Act warranties and a duty of care under the Design and Building Practitioners Act. Get legal advice on deadlines.
  • Evidence first. An independent BCA assessment or expert report is the foundation for every option.

What “not meeting the NCC” actually means

The NCC (which includes the Building Code of Australia) sets the minimum technical standards for building work. A building, or part of it, does not meet the NCC when it fails a Performance Requirement, and is neither built to the Deemed-to-Satisfy (DTS) Provisions nor supported by an approved Performance Solution.

In practice, people describe the same problem with different words, and the differences matter:

Non-compliance, defect and serious defect: how the terms differ
TermWhat it usually meansWhy it matters
Non-complianceWork that departs from the NCC or the approved plans, found by a certifier, consultant or purchaserMust be resolved before the Principal Certifier can issue an Occupation Certificate
DefectFaulty or non-compliant work, including work that breaches the statutory warranties under the Home Building Act 1989Can found claims against the builder or developer
Serious defectA defined category in NSW legislation covering defects in key building elements (such as fire safety systems, waterproofing, structure and the building enclosure), including a defect caused by non-compliance with the NCC Performance Requirements, Australian Standards or approved plans, and defects likely to make a building unusable, cause its destruction or threaten collapseCan trigger order powers, administered by Building Commission NSW, for Class 2 buildings and certain Class 3 and 9c buildings

Separately, a building that was approved and built to an earlier edition of the NCC is not “non-compliant” simply because the current NCC is different. Upgrade obligations arise in specific circumstances, covered below.

Your options at a glance

Options when a building does not meet the NCC in NSW
OptionWhen it suitsWhat is involved
Rectify to DTSThe work can practically be fixed to complyRepair or rebuild the non-compliant element, re-inspection by the certifier
Performance SolutionThe as-built work does not meet DTS but may meet the Performance Requirements, possibly with extra measuresSpecialist analysis and report, certifier assessment, and Fire and Rescue NSW consultation where the provisions require it
Modify the approvalThe change is acceptable in planning terms and can lawfully be approvedModification of the development consent or CDC, and updated construction approval, before the work is relied on
Regulatory actionThe responsible party will not fix the workComplaint to Building Commission NSW or council; orders may follow
Dispute resolutionOwners seeking rectification or compensationNegotiation, Building Commission NSW dispute resolution, NCAT or court, supported by expert evidence

When the non-compliance is found during construction

This is the best time to find it. The Principal Certifier carries out the required inspections at key stages and will raise non-compliances with the builder. Where work is not being carried out in accordance with the development consent, including the approved plans and conditions, a Principal Certifier other than a council must generally give a written direction to fix it (the Regulation sets some exceptions). If the direction is not complied with, the certifier must notify the consent authority, which has enforcement powers under the Environmental Planning and Assessment Act 1979.

Most importantly, the Principal Certifier cannot issue an Occupation Certificate unless the work is consistent with the development consent (which includes the approved construction plans) and the building is suitable for occupation or use for its classification. That is why unresolved non-compliances are one of the most common causes of Occupation Certificate delays. Our guide on how to get an Occupation Certificate in NSW explains what the certifier needs at the end.

Pro tip

Ask your certifier to put every non-compliance in writing with a reference to the NCC clause or approved plan it departs from. A clear list lets the builder, designer and any specialist decide quickly whether to rectify or to develop a Performance Solution.

Using a Performance Solution to resolve a non-compliance

Where rectifying the work would be impractical or would mean demolition, a Performance Solution may show that the as-built work still meets the NCC Performance Requirements. Common examples include fire separation details, smoke management, egress arrangements, stair geometry and access features.

A Performance Solution for as-built work must go through the same process as one developed at design stage: the right practitioner, an Assessment Method, a report, independent assessment by the certifier and, for a fire safety Performance Solution in most buildings other than houses, the Fire and Rescue NSW steps in the NSW process. It may also rely on additional measures, such as sprinklers, detection or management procedures, that then must be installed and maintained. Our guide What is a Performance Solution under the NCC? explains the process in detail.

Modifying the approval

Sometimes the issue is not the NCC but the approval: the building does not match the approved plans. Depending on the change, the options include modifying the development consent under section 4.55 of the EP&A Act, modifying a Complying Development Certificate, or updating the construction approval. The modification must be approved before the certifier can rely on it.

A modification is not a retrospective approval. If building work was carried out without any approval at all, a different set of rules applies. Our guide to unapproved building work in NSW covers that situation, including why there is no retrospective approval for building work in NSW.

What regulators can do

Building Commission NSW

For Class 2 (apartment) buildings, and certain Class 3 and Class 9c buildings, the Residential Apartment Buildings (Compliance and Enforcement Powers) Act 2020 gives the Secretary power, administered by Building Commission NSW, to investigate serious defects and make orders, including:

  • Building work rectification orders, requiring the developer (and potentially the builder or landowner) to fix serious defects, whether or not the building is occupied.
  • Prohibition orders, which can stop an Occupation Certificate being issued, for example where there is a serious defect.
  • Stop work orders where building work is being carried out in a way that could cause a serious defect.

The Commission can also issue rectification orders under the Home Building Act 1989, penalty notices and enforceable undertakings, and can prosecute. These powers apply to the building classes covered by the legislation; check the Commission’s current guidance for your building.

Council

Council can issue development control orders under the EP&A Act, for example to stop work, comply with an approval, or carry out fire safety work in an existing building.

Home building dispute resolution

For residential building work, Building Commission NSW offers a complaint and dispute resolution service between homeowners and licensed builders.

Your rights as an owner

Owners of residential buildings in NSW have several overlapping protections. The key ones are:

  • Statutory warranties under the Home Building Act 1989, which are implied into residential building contracts and include that work will be done with due care and skill, in accordance with the plans and the law, and will be fit for purpose. Different warranty periods apply to major and other defects.
  • Home building compensation cover, which can respond when a builder dies, disappears, becomes insolvent or has their licence suspended for failing to comply with a tribunal or court order to pay money, for work that requires it.
  • A statutory duty of care under Part 4 of the Design and Building Practitioners Act 2020, owed by people who carry out construction work to owners and subsequent owners, to avoid economic loss caused by defects.
  • NCAT (its Consumer and Commercial Division) and the courts, for orders to rectify work or pay compensation.
Watch for this

Claims and complaints are subject to time limits that depend on the type of defect, the type of claim and the building. Get legal advice early, and do not let a discussion with the builder run on without checking your position. Built Smart Solutions is not a law firm; we provide the technical evidence your lawyer will need.

Existing buildings and older editions of the NCC

A building is generally required to comply with the NCC edition that applied when it was approved. Changes to the NCC do not, by themselves, require existing buildings to be upgraded. Upgrades can be required in specific circumstances, including:

  • When a development application proposes building work or a change of use, and the consent authority requires fire safety or other upgrades as a condition, under the EP&A Regulation 2021.
  • When council issues a fire safety order for an existing building that does not provide adequate fire safety.
  • When alterations are approved: the work must not reduce the building’s fire protection and structural capacity, and a change of building use must meet the Category 1 fire safety provisions for the new use. Apart from a change of use, a certifier cannot require the rest of an existing building to be upgraded just because alterations are proposed.

Owners also have ongoing obligations to maintain essential fire safety measures and lodge annual fire safety statements. A BCA audit of an existing building identifies gaps before a purchase, lease, fit-out or change of use.

What to do when your building does not meet the NCC: step by step

  1. Get the non-compliance in writing

    Ask the certifier, inspector or consultant who identified it to describe it precisely, with the NCC clause or approved plan it departs from, and photographs.

  2. Commission an independent assessment

    Obtain a BCA assessment or expert report that confirms whether the work complies, how serious the issue is and what the realistic options are.

  3. Identify who is responsible

    Establish whether the designer, builder, developer, subcontractor or supplier is responsible, and what contracts, warranties and insurance apply.

  4. Choose a technical solution

    Decide between rectifying to DTS, developing a Performance Solution, or modifying the approval, considering safety, practicality and the impact on the program.

  5. Notify the responsible party

    Give written notice to the builder or developer with the evidence and a request to rectify, and keep a record of all correspondence.

  6. Escalate if needed

    If the work is not fixed, consider a complaint to Building Commission NSW or council, and get legal advice about NCAT or court proceedings and time limits.

  7. Have the solution approved and inspected

    Ensure any Performance Solution or modification is approved before it is relied on, and that rectified work is inspected and certified.

  8. Keep the records

    File the reports, approvals, certificates and correspondence with the building records for future owners, insurers and certifiers.

Why independent evidence matters

Every option above depends on credible evidence: what the NCC requires, what was built, why it does not comply, and what it would take to fix. That evidence must be independent of the people who designed or built the work.

Built Smart Solutions prepares BCA compliance assessments for owners and owners corporations, and our expert witness team provides independent opinion evidence on certification and NCC compliance for NCAT and court proceedings.

How Built Smart Solutions helps

Built Smart Solutions is a Sydney-based building certification and construction regulation firm. When a building does not meet the NCC, we can help in one role per project:

Our approach

On any one project we act as your consultant or your certifier, not both. That keeps every assessment independent, which matters most when compliance is in question. Why independence matters.

When a building does not meet the NCC: frequently asked questions

What happens if my building does not comply with the NCC?

The non-compliance must be resolved before the Principal Certifier can issue an Occupation Certificate. The main options are rectifying the work, developing a Performance Solution or modifying the approval. If the responsible party will not act, regulators, NCAT and the courts provide further routes.

Can a certifier approve work that does not meet the NCC?

No. A certifier cannot issue an Occupation Certificate for work that is inconsistent with the development consent, and the approved construction plans must themselves comply with the NCC. The work must be rectified, justified by an approved Performance Solution, or the approval lawfully modified.

Can a Performance Solution fix a non-compliance after it is built?

Sometimes. If the as-built work can be shown to meet the NCC Performance Requirements, possibly with additional measures, a Performance Solution can avoid demolition. It must be prepared by the right practitioner and assessed and approved by the certifier.

What is a serious defect in NSW?

A serious defect is a defined category in NSW legislation for defects in key building elements, such as fire safety systems, waterproofing, structure and the building enclosure. It includes a defect caused by non-compliance with the NCC Performance Requirements, Australian Standards or approved plans, and defects likely to make a building unusable, cause its destruction or threaten collapse. It can trigger order powers, administered by Building Commission NSW, for Class 2 buildings and certain Class 3 and 9c buildings.

What orders can Building Commission NSW issue?

For Class 2 buildings and certain Class 3 and 9c buildings, building work rectification orders, prohibition orders that can stop an Occupation Certificate being issued, and stop work orders are available. These are the Secretary’s powers, administered by Building Commission NSW. Home Building Act rectification orders, penalty notices and enforceable undertakings are also available.

Does my older building have to be upgraded to the current NCC?

Not automatically. A building generally needs to comply with the NCC that applied when it was approved. Upgrades can be required when you apply to alter it or change its use, or if council issues a fire safety order.

Who pays to fix a building that does not meet the NCC?

Usually the party responsible for the defective work, depending on contracts, statutory warranties, the duty of care under the Design and Building Practitioners Act and any insurance. Get legal advice about your rights and any time limits.

Do I need an expert report for an NCAT building dispute?

In most building disputes, yes. Independent expert evidence on what the NCC requires and what was built is central to proving a defect. Built Smart Solutions provides expert witness services on certification and NCC compliance.

Building doesn’t meet the NCC?

Independent BCA assessment, Performance Solution advice and expert evidence for owners, developers and owners corporations, from a Sydney team. ISO 9001 certified.

Written by the Built Smart Solutions certification and regulatory team, Sydney

Built Smart Solutions is a Sydney-based building certification and construction regulation firm working across Sydney and regional NSW: registered certifiers, town planners and consultants with 20+ years across certification, fire safety and regulatory policy, including private development and Crown building work. Registered under the Building and Development Certifiers Act 2018 (NSW), ISO 9001:2015 certified, members of the Association of Australian Certifiers. On any one project we act as your consultant or your certifier, not both. Meet the team · How we work · All services · FAQ

Reviewed by Tim O’Reilly, Managing Director, Built Smart Solutions. Registered Building Surveyor (Unrestricted), registration BDC 3184.

This guide reflects the NCC, the EP&A Act and Regulation, the Residential Apartment Buildings (Compliance and Enforcement Powers) Act 2020, the Home Building Act 1989, the Design and Building Practitioners Act 2020 and Building Commission NSW guidance as at 25 November 2026. It is general information, not legal advice; time limits apply to claims, so get legal advice about your situation. Nothing in this article is advice about a particular building. Legislative references were checked as at 25 November 2026. NSW rules change often, so confirm the current position before you rely on it. For advice on your project, contact Built Smart Solutions.

Liability limited by a scheme approved under Professional Standards Legislation.

Built Smart Solutions. Get Your Project Approved. Keep Your Building Compliant.