Unapproved Building Work in NSW: Buying or Selling a Property With Illegal Works, and Your Options
A practical guide for owners, buyers and sellers: what counts as unapproved building work in NSW, what council can do, why there is no such thing as retrospective approval, your options, what to do before buying or selling, strata issues, and how the Building (Approvals and Practitioners) Act 2026 tightens the rules. Written by the registered certifiers at Built Smart Solutions in Sydney and checked as at November 2026.
Quick answer
Unapproved building work in NSW is any work that needed a Complying Development Certificate, development consent or Construction Certificate but was built without one: for example an enclosed verandah, a garage converted into a room, an oversized deck or an unapproved granny flat. Council can issue orders under the Environmental Planning and Assessment Act 1979 requiring work to stop, or a building to be repaired, altered or demolished, or premises restored. There is no retrospective approval: a development consent has effect only from the date it is registered on the NSW Planning Portal, and a Construction Certificate has no effect if it is issued after the building work has physically commenced.
So the answer depends on the file: what was approved, what was built, and whether it complies. That is a question of evidence before it is a question of paperwork, and it differs from property to property. Built Smart Solutions, a Sydney-based building certification firm, assesses what was built against the Building Code of Australia and the approval history, and tells owners, buyers and sellers where they stand.
Key takeaways
- Unapproved is common. Enclosed verandahs, garage conversions, decks, retaining walls and granny flats are the usual culprits in Sydney homes.
- There is no retrospective approval. Consent has effect only from the date it is registered on the NSW Planning Portal, and a Construction Certificate issued after the work has started has no effect.
- The answer depends on the file. What was approved, what was built and whether it complies decide which options are realistic.
- Consent may still be needed going forward, for an ongoing use (such as a dwelling) or for rectification or new work.
- Buyers should look before exchange. The approval history and a pre-purchase inspection show what was approved and what was built.
- The rules are getting stricter. Under the Building (Approvals and Practitioners) Act 2026, once it commences, issuing a building approval for work already started will be an offence, and work already started will go through a separate post-commencement process.
- Built Smart Solutions assesses unapproved work against the Building Code of Australia, and identifies what must be fixed.
What counts as unapproved building work
Building work is unapproved when it needed an approval under the Environmental Planning and Assessment Act 1979 and did not get one, or was built differently from what was approved. That covers four situations:
- No approval at all: work that needed a CDC or development consent and Construction Certificate was simply built.
- “Exempt” that wasn’t: work built on the assumption it needed no approval, but which did not meet every exempt standard. See our guide to what you can build without approval.
- Built differently from the approval: a design changed on site beyond what the approval allows. See why a minor site change can stop your project cold.
- Approved but never signed off: approved work with no Occupation Certificate because inspections were missed or the project was abandoned.
The last category is different in law. It may be possible to complete the original approval rather than deal with it as unapproved work. See how to get an Occupation Certificate.
Common examples in Sydney homes
| Work | Why it often needed approval | Typical compliance issues |
|---|---|---|
| Enclosed verandah or deck converted to a room | Becomes habitable floor area of the house | Structure, ceiling height, light and ventilation, waterproofing, energy efficiency |
| Garage converted to a bedroom, studio or flat | Change from a Class 10a outbuilding to habitable space or a dwelling | Floor moisture, ceiling height, insulation, fire separation, smoke alarms |
| Granny flat or “studio” with kitchen and bathroom | A secondary dwelling always needs a CDC or DA | Fire separation, plumbing, BASIX, setbacks; see granny flat approval |
| Large or high deck | Exceeds exempt area or height limits | Structural adequacy, balustrade height, footings, setbacks |
| Retaining walls | Exceed exempt limits or support structures or boundaries | Engineering, drainage, effect on neighbours |
| Swimming pool | Only a small portable pool or spa (2,000 L or less) can be exempt | Pool barrier compliance, registration |
| Rumpus room or bathroom under the house | New habitable space or plumbing in a non-habitable area | Ceiling height, waterproofing, ventilation, egress |
| Attic or roof-space conversion | New habitable room | Stair, ceiling height, fire safety, structure |
| Commercial fit-out or change of use | Changes egress, fire safety or building classification | Exits, fire services, accessibility; see commercial CDCs |
What can happen if building work is unapproved
| Area | What can happen |
|---|---|
| Council action | Orders under the EP&A Act requiring work to stop, the building to be repaired, altered or demolished, or premises to be restored; penalty notices or prosecution. A consent authority is not obliged to act, but it can, and a complaint or a sale often prompts it |
| Selling | Buyers’ solicitors, lenders and building inspectors identify work without approval records; contracts may be renegotiated, delayed or rescinded depending on their terms |
| Buying | You inherit the problem, including any future council order |
| Insurance | Insurers may limit or refuse cover for uncertified work, and strata policies may exclude it |
| Finance | Lenders may value the property without the unapproved area or decline to lend |
| Renting | Letting an unapproved dwelling or room raises legal and insurance questions for the landlord; take advice |
| Strata | The owners corporation can enforce by-laws, including through the NSW Civil and Administrative Tribunal |
| Safety | Work that was never inspected may have hidden structural, waterproofing, electrical or fire safety defects |
The biggest risk with unapproved work is not the paperwork. It is that nobody independent checked the footings, framing, waterproofing or fire separation before they were covered. A compliance assessment often finds real defects, and those must be fixed whatever approval route you take.
Why there is no retrospective approval
Most people looking at unapproved work want a form that turns it into approved work. NSW law does not have one.
- Consent looks forward. A development consent authorises development to be carried out. It does not authorise work that has already been done.
- A late Construction Certificate does nothing. Under the Act, a Construction Certificate has no effect if it is issued after the building work it relates to has physically commenced.
- Doing nothing is not approval either. A consent authority is not obliged to take enforcement action, and often does not. That leaves the work unapproved, and the position can change when a neighbour complains, a buyer asks questions or the property is sold.
What that leaves is a judgement about the building itself: whether it complies, what it would take to make it comply, whether any part of it, or its use, needs consent from here on, and how the consent authority is likely to respond. Different routes have different consequences, and the right one depends on the facts of your file.
Get the evidence before you choose a route. A compliance assessment that identifies what complies, what does not and what needs opening up tells you which options are realistic, before anything is lodged and before a buyer’s solicitor asks the same questions. Built Smart Solutions prepares these assessments as a standalone service through our BCA consulting team.
Your options for unapproved work
| Option | When it fits | Notes |
|---|---|---|
| Retain the work, on the evidence | The work complies, or can be made to comply | Which route then applies depends on the file; take advice before lodging anything |
| Rectify | The work has defects that must be fixed | Rectification work itself may need approval; plan it before starting |
| DA for the use or for new work | The building is being used for a purpose that needs consent, such as a separate dwelling, or new work is needed | Consent has effect from when it is registered: it covers the use and any new work from then on, not the work already done |
| Remove and rebuild with approval | The work cannot reasonably be made compliant, or you want to redo it properly | Demolition of an unapproved structure may itself need approval; then a CDC or DA for the new work |
| Complete the original approval | Work was approved but never finished or signed off | Whether the OC can issue depends on the inspection record: a missed inspection can be excused only in unavoidable circumstances, and a missed final inspection cannot be excused at all; see replacing a PC |
A note on “retrospective DAs”: applications described this way are common, but consent has effect only from the date it is registered on the NSW Planning Portal. Whatever is lodged deals with the use and the work from then on. The work already carried out remains a question of evidence and of how the consent authority responds. Speak to a planner before lodging anything described as retrospective.
What to establish before you choose a route
Find out what was approved
Request the property’s approval history from council (DAs, Construction Certificates, CDCs, Occupation Certificates) and compare it with what is on site. A section 10.7 planning certificate also shows certain orders and notices.
Identify the unapproved elements
List each part of the building that has no approval or differs from its approval. Treat each element separately; some may be exempt and need nothing.
Get a survey and as-built plans
An identification survey and accurate plans of the building as it stands are needed for almost every route.
Commission a compliance assessment
A registered certifier or building surveyor assesses the work against the Building Code of Australia and identifies what complies, what does not and what investigation is needed (opening up, engineer’s inspection).
Take advice on the route
With the evidence in hand, decide what will be fixed, removed or retained, and which route fits. Some fixes are themselves building work that needs approval.
Buying or selling a property with unapproved work
If you are buying
- Read the section 10.7 certificate attached to the contract and ask for the approval history.
- Get a pre-purchase building inspection and ask the inspector to flag additions and conversions that may need approval records.
- Compare plans with the house. Extra bedrooms, enclosed areas and granny flats are the usual gaps.
- Talk to your conveyancer or solicitor about contract terms before exchange.
If you are selling
- Check your own approval history early. Problems found by a buyer’s solicitor weeks before settlement are harder to solve.
- Get a compliance assessment for anything without approval records, so you know what you are dealing with.
- Decide on a route early, with the compliance assessment in hand, so buyers and lenders get answers rather than questions.
- Take legal advice on disclosure and contract terms.
Built Smart Solutions does not give legal advice, but we work alongside conveyancers and solicitors, providing the technical assessment of what was built and what it would take to make it comply.
Unapproved work in strata buildings
In strata schemes, unapproved work raises two separate questions. The first is planning and building approval under the EP&A Act, as for any property. The second is the owners corporation’s approval under the Strata Schemes Management Act 2015 and the scheme’s by-laws, particularly for work affecting common property, waterproofing, structure or fire safety. Owners corporations can enforce by-laws, including through the NSW Civil and Administrative Tribunal. Bathroom renovations that disturb waterproofing, removed walls and enclosed balconies are common sources of these issues in Sydney apartments.
Where fire safety measures are affected, the building’s fire safety schedule and annual fire safety statement can also be affected. See our fire safety consultant guide.
What the Building (Approvals and Practitioners) Act 2026 changes
The Building (Approvals and Practitioners) Act 2026 received assent on 14 August 2026. Its main provisions commence on a day or days to be appointed by proclamation; as at 6 November 2026 no commencement proclamation had been made, and the current EP&A Act framework still applies. When the new regime commences:
- Construction Certificates become building approvals and Occupation Certificates become completion approvals;
- it becomes an offence to issue or vary a building approval for work that has already commenced, and an approval issued that way is void; work already started goes through a separate post-commencement authorisation process instead;
- occupying without a completion approval attracts penalties.
The direction is clear: dealing with work after the fact will be an exception with its own process and costs, not a routine step. Transitional arrangements will be set out in the regulations. We track the changes in Construction Certificates are being replaced and in Insights.
How to avoid unapproved work in the first place
- Check before you build. Confirm whether work is exempt, a CDC or a DA. See do I need council approval?
- Appoint your own Principal Certifier for approved work, and make sure every inspection happens.
- Do not change the design on site without checking it against the approval.
- Collect certificates as you go: waterproofing, electrical, structural, glazing.
- Get the Occupation Certificate before moving in or letting the space.
- Keep the paperwork with your property records for when you sell.
Common mistakes with unapproved work
Calling it “retrospective approval”
There is no such thing. Consent looks forward; the work already done is a question of evidence.
Choosing a route before the evidence
The compliance assessment decides which options are realistic. Doing it last costs time and money.
Covering up instead of investigating
Hidden defects found later cost more to fix and can derail a sale.
Treating a granny flat like a shed
A self-contained dwelling needs approval for its use as well as its structure.
Waiting until the property is on the market
Sorting out unapproved work takes time. Start before you list.
Rectifying without approval
Some fixes are themselves building work that needs approval. Plan them before starting.
How Built Smart Solutions helps
Built Smart Solutions is a Sydney-based building certification and construction regulation firm, ISO 9001 certified, with more than 20 years in certification and regulatory policy. Our role is to establish what was built, whether it complies, what must change and which route fits the facts.
| You need | Built Smart service |
|---|---|
| Advice on the options and strategy | Strategic Regulatory Guidance |
| A Building Code of Australia compliance assessment (standalone service) | BCA Consulting |
| Fire safety assessment for commercial or strata work | Fire Safety Strategy & Reports |
| A DA for the use, or planning advice | Town Planning |
| New approval for rebuilt or rectified work | Complying Development Certificates and Construction Certificates |
| Completing an approved but unfinished project | Principal Certifier and Occupation Certificates |
On any one project, Built Smart Solutions acts as your certifier or your consultant, not both, so the certification stays independent.
Honest assessment first: what complies, what doesn’t, and what it will take. Independent: on any one project we act as your certifier or your consultant, not both. Clear reports written for the people who will rely on them. Across Sydney and regional NSW. Meet the team.
Final verdict
Unapproved building work is common in Sydney and usually solvable, but there are no shortcuts. The work must be assessed honestly, defects fixed, and the route chosen from the evidence rather than from a form. Owners and buyers who start early, with a proper compliance assessment, get there faster and with fewer surprises. With the new Building Act on the way, the after-the-fact route will only get narrower.
If you have unapproved work, or have found it in a property you are buying or selling, Built Smart Solutions can assess it and map the way forward. See our regulatory guidance service, contact us or call (02) 9127 8249.
Frequently asked questions about unapproved building work in NSW
What is unapproved building work in NSW?
Building work that needed a Complying Development Certificate, development consent or Construction Certificate under the Environmental Planning and Assessment Act 1979 but was carried out without it, or was built differently from what was approved.
Can I get retrospective approval for building work in NSW?
No. A development consent has effect only from the date it is registered on the NSW Planning Portal, and a Construction Certificate has no effect if it is issued after the building work has physically commenced. A development application can deal with an ongoing use or with new or rectification work from then on, but not with the work already carried out. What is realistic depends on what was approved, what was built and whether it complies.
Does council have to take action against unapproved work?
No. A consent authority has power to make orders but is not obliged to, and often does not. That is not the same as the work being approved, and the position can change, for example when a neighbour complains or the property is sold.
Can council make me demolish unapproved work?
Council can issue development control orders under the EP&A Act requiring unapproved work to stop, or a building to be repaired, altered, restored or demolished. Whether it does depends on the work, its compliance and its impacts.
Can I sell a house with unapproved work?
Yes, but it can affect the price, the buyer’s finance and the timing of settlement, depending on the contract and what the buyer discovers. Getting a compliance assessment and deciding on a route before listing usually makes the sale smoother. Take legal advice on disclosure and contract terms.
I am buying a house with an unapproved extension. What should I do?
Ask for the approval history, read the section 10.7 certificate, get a pre-purchase building inspection and a compliance assessment, and speak to your conveyancer or solicitor before exchange about what the contract allows.
Is an unapproved granny flat a bigger problem than an unapproved deck?
Usually yes. A self-contained granny flat involves the use of the building as a dwelling as well as the structure, so consent may be needed for the use going forward, and fire separation, plumbing and amenity will be looked at closely.
What if my work was approved but never got an Occupation Certificate?
That is a different situation. It may be possible to complete the original approval and obtain the Occupation Certificate, but it depends on the inspection record: a missed inspection can be excused only in unavoidable circumstances, and a missed final inspection cannot be excused at all.
Does insurance cover unapproved building work?
Insurers may limit or refuse cover for unapproved or uncertified work, and strata policies may exclude it. Check your policy and disclose the work to your insurer.
What does the Building (Approvals and Practitioners) Act 2026 change for unapproved work?
Once its main provisions commence, issuing or varying a building approval for work that has already commenced becomes an offence and the approval is void; work already started goes through a separate post-commencement authorisation process. The Act received assent on 14 August 2026 and commences by proclamation; none had been made as at 6 November 2026.
How can Built Smart Solutions help with unapproved work?
Built Smart Solutions assesses unapproved work against the Building Code of Australia, identifies defects and rectification options, and advises on which route fits the facts, across Sydney and regional NSW. On any one project we act as your certifier or your consultant, not both, so the certification stays independent.
Found unapproved work?
An honest compliance assessment and a clear view of your options, from registered certifiers in Sydney. ISO 9001 certified.
Related reading from Built Smart Insights
This guide reflects the EP&A Act 1979, council practice and the status of the Building (Approvals and Practitioners) Act 2026 as at 6 November 2026. Council requirements vary. Nothing in this article is legal advice; speak to a solicitor or conveyancer about contracts and disclosure. Legislative references were checked as at 6 November 2026. For advice on your property, contact Built Smart Solutions.